Strategic planning for LEED certification
Author(s)
Capuzzi, Angelo Michael
DownloadFull printable version (9.924Mb)
Alternative title
Strategic planning for Leadership in Energy and Environmental Design certification
Other Contributors
Leaders for Global Operations Program.
Advisor
Daniel Whitney and Sara Beckman.
Terms of use
Metadata
Show full item recordAbstract
Intel Corporation has recently implemented a "green building" policy, which states that Intel will design all new facilities to achieve a minimum LEED-Silver certification. LEED (Leadership in Energy and Environmental Design) is a voluntary, consensus-driven rating system used to distinguish high performance, sustainable buildings. Buildings earn "points" in different environmental categories, and the total number of points achieved determines the certification level (Certified, Silver, Gold, or Platinum). While LEED certification has been successfully applied to many residential and commercial buildings, and occasionally to manufacturing facilities, it has not been applied to many wafer manufacturing facilities (fabs), which house the manufacturing and production of Intel's microprocessors. Wafer fabs have much higher energy and water consumption levels than typical buildings due to their strictly controlled temperature, humidity, and particulate requirements, making LEED certification more challenging for a fab than for a typical building. The objective of this study was to develop a planning strategy case study for Intel to achieve LEEDSilver certification for the construction of a hypothetical new wafer fab. The case study identified the main barriers to achieve LEED certification, including cost, risk, process, acceptance and alignment barriers, and outlined means to overcome them. The LEED criteria were then analyzed to determine the costs, benefits, and risks of pursuing each individual credit. The resulting "portfolio planning" model was then used to optimize a portfolio of credits for Intel to pursue. The final results indicated that for the optimized scenario, LEED-Silver certification could be achieved for a positive NPV of over $130,000. Significant cost savings were achieved through the avoidance of the credits related to energy efficiency and on-site renewable energy generation, credits that pose a significant risk to Intel due to the high energy consumption of a fab. Finally, process improvement recommendations were made for the planning, design, and construction of a LEED certified fab.
Description
Thesis (M.B.A.)--Massachusetts Institute of Technology, Sloan School of Management; and, (S.M.)--Massachusetts Institute of Technology, Engineering Systems Division; in conjunction with the Leaders for Global Operations Program at MIT, 2010. Cataloged from PDF version of thesis. Includes bibliographical references (p. 49-51).
Date issued
2010Department
Leaders for Global Operations Program at MIT; Massachusetts Institute of Technology. Engineering Systems Division; Sloan School of ManagementPublisher
Massachusetts Institute of Technology
Keywords
Sloan School of Management., Engineering Systems Division., Leaders for Global Operations Program.